Pacific Booker Minerals Inc. Announces Response to Ministry of Environment
Posted
Vancouver BC, October 31, 2012: The Company has responded to the Ministry
of Environment in regards to the rejection of the Company’s Application for an
Environmental Assessment Certificate.
The Company has been working on the development of the Morrison Copper/Gold
Project (the Project) since 1998. Baseline data to support the Application for
an Environmental Assessment Certificate (EAC) has been collected since 2002. PBM
entered the Pre-Application stage of the Environmental Assessment Process on
September 30, 2003.
On July 12, 2010, PBM entered the Application Review stage of the Environmental
Assessment process when the BC Environmental Assessment Office (EAO) accepted
the Company’s Application for an EAC.
On August 20, 2012, day 763 of the 180-day Review period, the EAO completed the
Environmental Assessment Application Review and submitted their referral
documents to the Ministers for a decision.
On October 1, 2012, the Application was rejected by the Ministers although the
EAO’s Assessment Report concluded that the Project as proposed does not have the
potential for significant adverse effects and that the First Nations have been
consulted and accommodated appropriately.
The Company’s responses to the factors that were considered by the Ministers in
reaching their decision, (as per the e-mail from Terry Lake, Minister of
Environment received October 1, 2012) have been prepared, emailed to the
appropriate ministers and posted on the Company’s website at the following link:
http://www.pacificbooker.com/pdf/121030L-MorrisonEACRejectionResponse.pdf .
The Company wishes to emphasize that the design and environmental assessment of
the Project was prepared by qualified professionals who have extensive
world-wide experience. In addition, independent 3rd Party reviews, initiated by
the EAO, supported PBM’s assessment of no significant adverse effects.
PBM has adequately and reasonably addressed all the issues raised by government
agencies, First Nations and the public (over 70 government agency reviewers,
nine organizations and over 800 issues/comments).
The Application contained approximately 16,000 pages including the EAC
Application; an Addendum to the EAC Application; Review Response Report Rev 1;
Review Response Report Rev 2; 3rd Party Review Response Report and 3rd Party
Review Response Report Addendum.
The EAO and the Company agreed to 32 Conditions that PBM would have to meet as
part of the EAC. The information and plans would be developed during the
Detailed Engineering phase, which PBM has not yet started, and would be
completed prior to the issuance of the Mines Act Permit.
In a letter to the EAO on August 13, 2012, the Company summarized its final
response with respect to the EAC Application. In that letter, PBM noted that the
changes in predicted Morrison Lake metal concentrations, using upper bound
loadings, due to the project are below BC Water Quality Guidelines and nominally
above baseline, and the risk of a significant adverse effect is, therefore,
negligible and that the design is protective of the aquatic environment.
The Company wishes to emphasize that PBM is strongly committed to continue to
work towards bringing the proposed Morrison Copper/Gold Project to commercial
production.